The Great Northern Highway Realignment Project involved realigning an 8km section of a major road around the Wedgefield industrial area in Port Hedland in Western Australia’s remote Pilbara region. The project scope also included a major road interchange, a new road bridge over BHP’s iron ore rail line, a level bridge at South Creek, and new intersections.
JAGCON Group provided short-term support during the critical start-up phase, including setting up for key project delivery areas and awarding subcontracts. JAGCON Group revised the program and planning to avoid a second wet season, which saw the project finish six months early.
JAGCON Group worked with Macmahon Contractors providing project management services, expert advice on constructability & senior engineers throughout the lifecycle of the project.
Key Construction Works:
– Earthworks (Surface)
– Surface Roadworks & Drainage
– Site Development & Establishment
Project Delivery Roles:
– Earthworks/Roads Manager